Buildings and Facilities22M00129

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SUGADOL, DATU ABDULLAH SANGKI , MAGUINDANAO.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SUGADOL, DATU ABDULLAH SANGKI , MAGUINDANAO. is a DPWH-tracked public work in Region XII, Region XII. Reported contract value: ₱4,932,978.90. Status: Reported complete (DPWH). Contractor on record: ARGE CONST AND SUPPLY. Figures trace to dpwh.

Region XII, Region XII
Region: Region XII

Follow the peso

1 of 5 steps linked to this project. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    No GAA line found for this project's office and year. The GAA lists budgets by program and office, not always by project.

  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 22M00129 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-11-26 → 2025-11-23

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION  OF MULTI-PURPOSE BUILDING, BRGY. SUGADOL, DATU ABDULLAH SANGKI , MAGUINDANAO.

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱4,932,978.90

Progress

Reported complete (DPWH)

Start Date

November 16, 2022

Target End

February 28, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.