Buildings and Facilities18KG0050

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. KALANGANAN, LOWER PANTAR, PANTAR, LANAO DEL NORTE

CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. KALANGANAN, LOWER PANTAR, PANTAR, LANAO DEL NORTE is a DPWH-tracked public work in Lanao del Norte 2nd DEO, Region X. Reported contract value: ₱1,440,052.71. Status: Reported complete (DPWH). Contractor on record: LANAO GENESIS CONST SUPPLY. Figures trace to dpwh.

Lanao del Norte 2nd DEO, Region X
Region: Region X

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱5,000

    Probable match · score 0.87

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-D-18-0014700 · ₱220,000,000 · release to the district office, not itemized per project

    Possible match · score 0.70

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱1,440,053 · LANAO GENESIS CONSTRUCTION SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-05-21 → 2025-11-06

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF MULTI-PURPOSE BUILDING AT BRGY. KALANGANAN, LOWER PANTAR, PANTAR, LANAO DEL NORTE

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 87%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control, Brgy. Marinding, Municipality of Lala, Lanao del Norte
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-D-18-0014700

₱220,000,000.00 · FY2018

Released to Philippine Army ( rces ) Forces ) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱1,440,052.71

Progress

Reported complete (DPWH)

Start Date

May 24, 2018

Target End

July 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.