Water Provision and Storage23F00307

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF VARIOUS SOLAR WATER SYSTEM LEVEL II, IN THE MUNICIPALITY OF OAS, ALBAY, SAN MIGUEL, CAMAGONG, BANAO AND TOBGON,O

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP)-BASIC INFRASTRUCTURE PROGRAM (BIP)-PUBLIC WATER SUPPLY SYSTEM (LEVEL II OR III)-CONSTRUCTION OF VARIOUS SOLAR WATER SYSTEM LEVEL II, IN THE MUNICIPALITY OF OAS, ALBAY, SAN MIGUEL, CAMAGONG, BANAO AND TOBGON,O is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱19,208,465.14. Status: Past target date (DPWH On-Going). Contractor on record: EARTHLINE CONST. Figures trace to dpwh.

Region V, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

4. Implementation

Contract Amount

₱19,208,465.14

Progress

Past target date (DPWH On-Going)

Start Date

September 22, 2023

Target End

January 29, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.