GAA 2019 OO-119LH0023

PAVING OF SHOULDER ALONG EDEN-TAGURANO ROAD, K1537+586 TO K1537+804, 3RD CONGRESSIONAL DISTRICT, DAVAO CITY

PAVING OF SHOULDER ALONG EDEN-TAGURANO ROAD, K1537+586 TO K1537+804, 3RD CONGRESSIONAL DISTRICT, DAVAO CITY is a DPWH-tracked public work in Davao City 2nd DEO, Region XI. Reported contract value: ₱4,718,794.10. Status: Reported complete (DPWH). Contractor on record: LLM UNIFIED BUILDERS. Figures trace to dpwh.

Davao City 2nd DEO, Region XI
Region: Region XI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-NCR-19-0001936

₱307,728.00 · FY2019

Released to Division of Quezon City (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱4,718,794.10

Progress

Reported complete (DPWH)

Start Date

July 12, 2019

Target End

August 17, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.