GAA 2024 OO-224PL0130

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE CANAL ALONG MT. PROVINCE BDRY. - CALANAN - PINUKPUK - ABBUT ROAD, CALANAN-PINUKPUK JUNCTION S

ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE CANAL ALONG MT. PROVINCE BDRY. - CALANAN - PINUKPUK - ABBUT ROAD, CALANAN-PINUKPUK JUNCTION S is a DPWH-tracked public work in Lower Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱27,366,450.08. Status: Past target date (DPWH On-Going). Contractor on record: CALANAN RISING CONST. Figures trace to dpwh.

Lower Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images pending: this project is in the imagery queue (completed projects first, then ongoing). Before/after images will appear here when it is processed.

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2024 · ₱5,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 24PL0130 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    99% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ORGANIZATIONAL OUTCOME 2: PROTECT LIVES AND PROPERTIES - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF DRAINAGE CANAL ALONG MT. PROVINCE BDRY. - CALANAN - PINUKPUK - ABBUT ROAD, CALANAN-PINUKPUK JUNCTION S

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱5,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Turayok Creek Barangay Catabbogan, Pinukpuk, Kalinga
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Lower Kalinga DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

5 projects · ₱46.1M total · 0 flags

4. Implementation

Contract Amount

₱27,366,450.08

Progress

Past target date (DPWH On-Going)

Start Date

December 17, 2024

Target End

August 24, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.