Water Provision and Storage23F00295

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTION SYSTEM, PROVINCE OF CAMARINES NORTE (2ND LEGISLATIVE DISTRICT)

CONVERGENCE AND SPECIAL SUPPORT PROGRAM (CSSP) - CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTION SYSTEM, PROVINCE OF CAMARINES NORTE (2ND LEGISLATIVE DISTRICT) is a DPWH-tracked public work in Region V, Region V. Reported contract value: ₱2,281,328.56. Status: Reported complete (DPWH). Contractor on record: 888RV CONST AND SUPPLIES. Figures trace to dpwh.

Region V, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2023 GAA. DBM GAA FY2023

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

113 projects · ₱811.7M total · 0 flags

4. Implementation

Contract Amount

₱2,281,328.56

Progress

Reported complete (DPWH)

Start Date

September 29, 2023

Target End

November 27, 2023

5. Audit