Flood Control and Drainage24DN0119

CONSTRUCTION OF BOX CULVERT AT BANABA CREEK, BRGY. SAN LUIS ANTIPOLO CITY (SECOND DISTRICT)

CONSTRUCTION OF BOX CULVERT AT BANABA CREEK, BRGY. SAN LUIS ANTIPOLO CITY (SECOND DISTRICT) is a DPWH-tracked public work in Rizal 1st DEO, Region IV-A. Reported contract value: ₱9,601,996.14. Status: Past target date (DPWH On-Going). Contractor on record: FIDEM DEVELOPMENT CORP. Figures trace to dpwh.

Rizal 1st DEO, Region IV-A
Region: Region IV-A

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Sta. Cruz, Antipolo City
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Agency-level releases for FY2024, not tied to this contract

Rizal 1st DEO · SARO 1,917 (₱267,033,855,698.00) · NCA 1,287 (₱846,238,484,493.07)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

13 projects · ₱152.6M total · 0 flags

4. Implementation

Contract Amount

₱9,601,996.14

Progress

Past target date (DPWH On-Going)

Start Date

April 29, 2024

Target End

November 24, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.