Flood Control and Drainage15CA0103

CONSTRUCTION/IMPROVEMENT OF COLO RIVER (SAN BENITO SECTION), DINALUPIHAN, BATAAN

CONSTRUCTION/IMPROVEMENT OF COLO RIVER (SAN BENITO SECTION), DINALUPIHAN, BATAAN is a DPWH-tracked public work in Bataan 1st DEO, Region III. Reported contract value: ₱13,671,000.00. Status: Reported complete (DPWH). Contractor on record: HORAMABI BUILDERS. Figures trace to dpwh.

Bataan 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 79%

UACS
18001
Amount
₱15,838,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures Slope Protection, Cataning River, Balanga City, Bataan
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-C-16-0028191

₱2,341,985.00 · FY2016

Released to 0000 - Presidential Communications Operations Office (PTo co (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Possible match · 68%

Mobilization/Demobilization

₱50,000.00 · HORAMABI BUILDERS

Contractor

C

27 projects · ₱1.5B total · 0 flags

Other projects by this contractor

View all 27 projects →

4. Implementation

Contract Amount

₱13,671,000.00

Progress

Reported complete (DPWH)

Start Date

February 18, 2016

Target End

July 16, 2016

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.