Water Provision and Storage23JA0074

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM -CONSTRUCTION OF SOLAR WATER SYSTEM IN BRGY. LAPAKAN, ZAMBOANGA CITY

CONSTRUCTION/REHABILITATION OF WATER SUPPLY/SEPTAGE AND SEWERAGE/RAIN WATER COLLECTORS - WATER SUPPLY SYSTEM -CONSTRUCTION OF SOLAR WATER SYSTEM IN BRGY. LAPAKAN, ZAMBOANGA CITY is a DPWH-tracked public work in Zamboanga City 2nd DEO, Region IX. Reported contract value: ₱9,309,997.90. Status: Past target date (DPWH On-Going). Contractor on record: ASAP GEN TRADING CONST. Figures trace to dpwh.

Zamboanga City 2nd DEO, Region IX
Region: Region IX

Satellite images processing — before/after tiles will appear here after the next batch run.

Follow the peso

2 of 5 steps linked from public records. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2023 · ₱50,000

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    Not yet linked

  3. 3. PhilGEPS award

    Not yet linked

  4. 4. DPWH progress + satellite

    95% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH source ↗
  5. 5. COA audit finding

    Not yet linked

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Bunguiao Flood Control Structure, Zamboanga City
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zamboanga City 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

D

11 projects · ₱165.4M total · 0 flags

Other projects by this contractor

View all 11 projects →

4. Implementation

Contract Amount

₱9,309,997.90

Progress

Past target date (DPWH On-Going)

Start Date

January 11, 2024

Target End

September 12, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.