Construction of Flood Mitigation Structure, Iraan River Waterways Phase 3, Left Bank Sta. 0+000 - Sta. 0+380, Right Bank Sta. 0+107 - Sta. 0+364, Upper Left Bank Sta. 0+389 - Sta. 0+503, Aborlan, Palawan
Construction of Flood Mitigation Structure, Iraan River Waterways Phase 3, Left Bank Sta. 0+000 - Sta. 0+380, Right Bank Sta. 0+107 - Sta. 0+364, Upper Left Bank Sta. 0+389 - Sta. 0+503, Aborlan, Palawan is a DPWH-tracked public work in ABORLAN (PALAWAN), PALAWAN, Region IV-B. Reported contract value: ₱96,496,704.82. Status: Reported complete (DPWH). Contractor on record: HARDROCKPLATINUM DEVELOPMENT CORP / C T LEONCIO CONST & TRADING. Figures trace to sumbong.
Total Contract Cost