Flood Control and Drainage18CK0014

REHAB/IMPT OF EXISTING DIKE ALONG LUCUNG RIVER (SAN JOSE SECT., R/B), D/S OF LUCUNG BR., CONC., TAR.

REHAB/IMPT OF EXISTING DIKE ALONG LUCUNG RIVER (SAN JOSE SECT., R/B), D/S OF LUCUNG BR., CONC., TAR. is a DPWH-tracked public work in Tarlac 2nd DEO, Region III. Reported contract value: ₱18,615,521.05. Status: Reported complete (DPWH). Contractor on record: B K SY TU CONST. Figures trace to dpwh.

Tarlac 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation/Improvement of Existing Dike along Lucung River (San Jose, Right Bank, D/S of Lucung Bridge), Sta. 0+390 to Sta. 0+640, Concepcion, Tarlac
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIII-18-0029562

₱0.00 · FY2018

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱18,615,521.05

Progress

Reported complete (DPWH)

Start Date

February 1, 2018

Target End

June 1, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.