Roads21PD0015

OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-QUIRINO H-WAY (BAGUIO -BAUANG), K0303+951-K0305+860

OFF-CARRIAGEWAY IMPROVEMENT-PRIMARY ROADS-QUIRINO H-WAY (BAGUIO -BAUANG), K0303+951-K0305+860 is a DPWH-tracked public work in Baguio City DEO, Cordillera Administrative Region. Reported contract value: ₱6,091,392.04. Status: Reported complete (DPWH). Contractor on record: HDG CONST AND ENT. Figures trace to dpwh.

Baguio City DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction (Continuation) of the Flood Control along Bued River (concrete wall near AGAPE Family Christian Church) at Camp 7 Barangay, Camp 7 Barangay, Baguio City
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Baguio City DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

26 projects · ₱151.5M total · 0 flags

4. Implementation

Contract Amount

₱6,091,392.04

Progress

Reported complete (DPWH)

Start Date

April 8, 2021

Target End

September 29, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.