Roads22A00106

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS ( TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP ), MARUAYA-DUPITAC-CALAMBEG ESTANCIA ROAD LEADING TO LOWLAND COFFEE CONVERGENCE INITIATIVE PROJECT, BRGY. MARUAYA, PIDDIG, ILOCO

CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO DECLARED TOURISM DESTINATIONS ( TOURISM ROAD INFRASTRUCTURE PROGRAM - TRIP ), MARUAYA-DUPITAC-CALAMBEG ESTANCIA ROAD LEADING TO LOWLAND COFFEE CONVERGENCE INITIATIVE PROJECT, BRGY. MARUAYA, PIDDIG, ILOCO is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱3,859,969.89. Status: Reported complete (DPWH). Contractor on record: BJMJB CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2022 GAA. DBM GAA FY2022

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

360 projects · ₱4.5B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD MITIGATING STRUCTURE RIGHT BANK, BARANGAY ISIC-ISIC, VINTAR ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱57.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATIONSTRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OFFLOOD CONTROL STRUCTURE ALONG PADSAN RIVER, BARANGAY10, SARRAT, ILOCOS NORTE (PHASE 2)

Ilocos Norte 1st DEO, Region I

2024₱57.9M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, SITIO DALIM, BARANGAY CABAYO, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱56.4M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BISLAK RIVER, SANJERA BENGBENGKAG, BARANGAY ISIC-ISIC, VINTAR, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱56.1M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG DAURAO CREEK, BARANGAY CAAOACAN, LAOAG CITY, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱55.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, CONSTRUCTION OF FLOOD CONTROL STRUCTURE MANGATO BRIDGE UPSTREAM, LAOAG CITY, ILOCOS NORTE

Ilocos Norte 1st DEO, Region I

2025₱55.6M
Past target date (DPWH On-Going)
View all 360 projects →

4. Implementation

Contract Amount

₱3,859,969.89

Progress

Reported complete (DPWH)

Start Date

March 4, 2022

Target End

April 7, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.