Roads19HM0029

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, LAMBOJON ROAD CONNECTING TO MANUFACTURING SITE AND SIQUIJOR PROVINCIAL ROAD IN SUPPORT OF FURNITURE INDUSTRIES, LAMBOJON, SI

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-CONSTRUCTION/IMPROVEMENT OF ACCESS ROADS LEADING TO TRADES, INDUSTRIES AND ECONOMIC ZONES, LAMBOJON ROAD CONNECTING TO MANUFACTURING SITE AND SIQUIJOR PROVINCIAL ROAD IN SUPPORT OF FURNITURE INDUSTRIES, LAMBOJON, SI is a DPWH-tracked public work in Siquijor DEO, Negros Island Region. Reported contract value: ₱8,649,440.00. Status: Reported complete (DPWH). Contractor on record: WTG CONST. Figures trace to dpwh.

Siquijor DEO, Negros Island Region
Region: Negros Island Region

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROII-19-0006566

₱18,488.00 · FY2019

Released to School (Isabela National High School - Villaluna Annex) (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

298 projects · ₱12.8B total · 0 flags

Other projects by this contractor

CONSTRUCTION OF STORM SURGE PROTECTION: HEIGHTENED ROAD AND TIDE EMBANKMENT, STATION 1+900 - STATION 2+550, SECTION 5 PHASE 9, BRGY. SAN JOAQUIN, PALO, LEYTE

Region VIII, Region VIII

2018₱263.4M
Reported complete (DPWH)

CONSTRUCTION OF FLOOD MITIGATION FACILITIES ALONG MAJOR RIVER BASINS AND PRINCIPAL RIVERS AT SIPALAY RIVER

Region VI, Region VI

2018₱195.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM-CONSTRUCTION OF FLYOVERS/INTERCHANGES/UNDERPASSES/LONG SPAN BRIDGES PANGLAO-TAGBILARAN CITY OFFSHORE BRIDGE, SECTION 1: STA.000+000-STA.000+223.21, SECTION

Region VII, Region VII

2020₱193.0M
Reported complete (DPWH)
No sat.

CSSP, SUSTAINABLE INFRA PROJ. ALLEVIATING GAPS (SIPAG)-ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/ STRATEGIC PUBLIC BLDG./ FACILITIES, CONST. OF ROAD FROM TABON TO BARANGAY GUBA LEADING TO BINAKAYAN, VALLEHERMOSO,NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PINOCAWAN RIVER, VALLEHERMOSO, NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
No sat.

CSSP, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BATERIA RIVER, GUIHULNGAN CITY, NEGROS ORIENTAL

Region VII, Region VII

2024₱193.0M
Past target date (DPWH On-Going)
View all 298 projects →

4. Implementation

Contract Amount

₱8,649,440.00

Progress

Reported complete (DPWH)

Start Date

June 28, 2019

Target End

September 5, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.