Flood Control and Drainage25HO0015

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL ALONG PARALE RIVER (UPSTREAM), BARANGAY SALMERO

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), FLOOD MITIGATION STRUCTURES PROTECTING PUBLIC INFRASTRUCTURES/FACILITIES, CONSTRUCTION OF REVETMENT WALL ALONG PARALE RIVER (UPSTREAM), BARANGAY SALMERO is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱72,271,888.00. Status: Past target date (DPWH On-Going). Contractor on record: QUIRANTE CONST CORP FORMERLY: QUIRANTE CONST. Figures trace to dpwh.

Cebu 7th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱150,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Tubod River Flood Control, Barangay Tubod-Duguan, Dumanjug, Cebu (Phase 3)
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 7th DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

409 projects · ₱18.8B total · 42 flags

4. Implementation

Contract Amount

₱72,271,888.00

Progress

Past target date (DPWH On-Going)

Start Date

February 28, 2025

Target End

November 17, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.