Buildings and Facilities23JF0069

CONSTRUCTION OF PNP PPO MULTI-PURPOSE BUILDING WITH AMENITIES, BARANGAY PANGI, IPIL, ZAMBOANGA SIBUGAY

CONSTRUCTION OF PNP PPO MULTI-PURPOSE BUILDING WITH AMENITIES, BARANGAY PANGI, IPIL, ZAMBOANGA SIBUGAY is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱4,942,540.65. Status: Reported complete (DPWH). Contractor on record: BARILLO CONST AND ENT. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control along Sibuguey River, Barangay Villacastor, Buug, Zamboanga Sibugay Package 3
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zamboanga Sibugay 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

140 projects · ₱2.5B total · 0 flags

Other projects by this contractor

CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - REHABILITATION/IMPROVEMENT OF FLOOD CONTROL FOR PREVENTION AND MITIGATION ALONG BRGY. SAN JOSE-POBLACION IMELDA, PART OF SIBUGUEY RIVER, IMELDA, Z

Region IX, Region IX

2019₱112.1M
Reported complete (DPWH)

CONSTRUCTION/MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF FLOOD CONTROL ALONG KABASALAN RIVER (PHASE III), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2021₱105.1M
Reported complete (DPWH)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE IV), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY

Region IX, Region IX

2022₱104.9M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱104.8M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), DOWNSTREAM, CANACAN, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 2

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVERS BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG KABASALAN RIVER (PHASE V), FL PENA, KABASALAN, ZAMBOANGA SIBUGAY, PACKAGE 1

Region IX, Region IX

2023₱100.0M
Reported complete (100% progress, DPWH status On-Going)
View all 140 projects →

4. Implementation

Contract Amount

₱4,942,540.65

Progress

Reported complete (DPWH)

Start Date

July 31, 2023

Target End

December 27, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.