Buildings and Facilities19EG0058

COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. SAN JUAN, ABORLAN, PALAWAN

COMPLETION OF MULTI-PURPOSE BUILDING (COVERED COURT) AT BRGY. SAN JUAN, ABORLAN, PALAWAN is a DPWH-tracked public work in Palawan 3rd DEO, Region IV-B. Reported contract value: ₱2,726,027.07. Status: Reported complete (DPWH). Contractor on record: SEVEN DIGIT CONST AND TRUCKING SERVICES CORP FORMERLY: SEVEN DIGIT CONST. Figures trace to dpwh.

Palawan 3rd DEO, Region IV-B
Region: Region IV-B

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROV-19-0005439

₱11,776,013.00 · FY2019

Released to Regional Office - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

52 projects · ₱745.5M total · 0 flags

4. Implementation

Contract Amount

₱2,726,027.07

Progress

Reported complete (DPWH)

Start Date

August 16, 2019

Target End

November 13, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.