Buildings and Facilities18BD0129

CONSTRUCTION OF TWO (2) STOREY EIGHT (8) CLASSROOM TWO (2) CLASSROOM SCIENCE LABORATORY AND TWO (2) CLASSROOM ICT, VICENTE D. TRINIDAD HIGH SCHOOL, IGUIG, CAGAYAN

CONSTRUCTION OF TWO (2) STOREY EIGHT (8) CLASSROOM TWO (2) CLASSROOM SCIENCE LABORATORY AND TWO (2) CLASSROOM ICT, VICENTE D. TRINIDAD HIGH SCHOOL, IGUIG, CAGAYAN is a DPWH-tracked public work in Cagayan 3rd DEO, Region II. Reported contract value: ₱15,816,313.26. Status: Reported complete (DPWH). Contractor on record: ROGELIO M DIMAANDAL CONST. Figures trace to dpwh.

Cagayan 3rd DEO, Region II
Region: Region II

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System (Downstream), Natappian, Solana, Cagayan
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROII-18-0002813

₱6,117,152.00 · FY2018

Released to Regional Office - II (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

15 projects · ₱353.9M total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES MULTIPURPOSE/FACILITIES - CONSTRUCTION OF MEGA ISOLATION FACILITIES, TUGUEGARAO CITY, CAGAYAN

Cagayan 3rd DEO, Region II

2022₱72.4M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM: BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES-NATIONAL BUILDING PROGRAM: CONSTRUCTION /EXTENSION OF DPWH-REGIONAL OFFICE II BUILDING, REG'L GOV'T CENTER, CARIG SUR, TUGUEGARAO CITY, CAGAYAN

Region II, Region II

2019₱48.2M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/FACILITIES - CONSTRUCTION OF TWO-STOREY BUILDING (DPWH) STANDARD DESIGN) OF CAGAYAN 3RD DISTRICT ENGINEERING OFFICE, TUGUEGARAO CITY, CAGAYAN

Cagayan 3rd DEO, Region II

2020₱37.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF THREE (3) STOREY TWELVE (12) CLASSROOM (TWO (2) REGULAR WORKSHOP/TWO (2) CLASSROOM SCIENCE LABORATORY & TWO (2) CLASSROOM ICT), GADU NATIONAL HIGH SCHOOL-NANGALISAN EXTENSION, SOLANA, CAGAYAN

Cagayan 3rd DEO, Region II

2018₱29.0M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF THREE (3) STOREY TWELVE (12) CLASSROOM (TWO (2)CLASSROOM SCIENCE LABORATORY/TWO (2) CLASSROOM ICT & TWO (2) CLASSROOM REGULAR WORKSHOP BUILDING), GAMMAD NATIONAL HIGH SCHOOL, IGUIG, CAGAYAN

Cagayan 3rd DEO, Region II

2018₱27.0M
Reported complete (DPWH)
No sat.

LOCAL PROGRAM - NATIONAL BUILDING PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTI-PURPOSE/FACILITIES - CONSTRUCTION (COMPLETION) OF DORMITORY AT CSU CARIG, TUGUEGARAO CITY, CAGAYAN

Cagayan 3rd DEO, Region II

2023₱19.5M
Reported complete (DPWH)
View all 15 projects →

4. Implementation

Contract Amount

₱15,816,313.26

Progress

Reported complete (DPWH)

Start Date

July 16, 2018

Target End

January 11, 2019

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.