COMPLETION OF MULTIPURPOSE BUILDING, MAGSAYSAY, QUEZON, BUKIDNON

COMPLETION OF MULTIPURPOSE BUILDING, MAGSAYSAY, QUEZON, BUKIDNON is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱2,458,222.96. Status: Reported complete (DPWH). Contractor on record: CAGALAWAN ENT. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Follow the peso

2 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2022 · ₱35,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    ₱2,458,223 · CAGALAWAN ENTERPRISES

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-07-28 → 2024-01-24

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: COMPLETION OF MULTIPURPOSE BUILDING, MAGSAYSAY, QUEZON, BUKIDNON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Sagayaran Bridge including approaches and flood control, Kinura, Kalilangan, Bukidnon (Phase 1)
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Bukidnon 2nd DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

4. Implementation

Contract Amount

₱2,458,222.96

Progress

Reported complete (DPWH)

Start Date

April 6, 2022

Target End

July 19, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.