Buildings and Facilities21HN0088

LP: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES -MULTIPURPOSE/FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PITOGO, CONSOLACION, CEBU

LP: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES -MULTIPURPOSE/FACILITIES - CONSTRUCTION OF MULTI-PURPOSE BUILDING, BARANGAY PITOGO, CONSOLACION, CEBU is a DPWH-tracked public work in Cebu 6th DEO, Region VII. Reported contract value: ₱0.00. Status: Past target date (DPWH On-Going). Contractor on record: BANTAY CONST. Figures trace to dpwh.

Cebu 6th DEO, Region VII
Region: Region VII

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱1,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control and Drainage System, Barangay Tilhaong, Consolacion, Cebu
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Cebu 6th DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

119 projects · ₱682.0M total · 0 flags

4. Implementation

Contract Amount

₱0.00

Progress

Past target date (DPWH On-Going)

Start Date

April 22, 2021

Target End

July 5, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.