Flood Control and Drainage17CE0083

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG TALAVERA RIVER BRGY. STA. MONICA, ALIAGA, NUEVA ECIJA, STA. 102+395.98 - STA. 102+533.67, STA. 103+206.99 - STA. 103+262.50

CONSTRUCTION/REHABILITATION OF FLOOD CONTROL STRUCTURES ALONG TALAVERA RIVER BRGY. STA. MONICA, ALIAGA, NUEVA ECIJA, STA. 102+395.98 - STA. 102+533.67, STA. 103+206.99 - STA. 103+262.50 is a DPWH-tracked public work in Nueva Ecija 1st DEO, Region III. Reported contract value: ₱26,684,055.38. Status: Reported complete (DPWH). Contractor on record: DGSARM BUILDERS INC FORMERLY: D G SARMENTA CONST. Figures trace to dpwh.

Nueva Ecija 1st DEO, Region III
Region: Region III

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 88%

UACS
18001
Amount
₱35,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structures along Talavera River at Brgy. San Eustacio, Aliaga, Nueva Ecija
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROXI-17-0021110

₱165,685.00 · FY2017

Released to Laak National High Mo School (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

A

145 projects · ₱2.7B total · 5 flags

4. Implementation

Contract Amount

₱26,684,055.38

Progress

Reported complete (DPWH)

Start Date

September 24, 2017

Target End

March 22, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.