Buildings and Facilities16MG0129

CONSTRUCTION OF 2 UNITS-1STY 3CL AT PROPER NED ES, LAKE SEBU, SOUTH COTABATO

CONSTRUCTION OF 2 UNITS-1STY 3CL AT PROPER NED ES, LAKE SEBU, SOUTH COTABATO is a DPWH-tracked public work in South Cotabato 2nd DEO, Region XII. Reported contract value: ₱6,216,576.27. Status: Reported complete (DPWH). Contractor on record: C E K CONST AND WATER SUPPLY. Figures trace to dpwh.

South Cotabato 2nd DEO, Region XII
Region: Region XII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱21,420,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Slope Protection) to Protect Lower Silway Bridge, Brgy. Labanggal, General Santos City, South Cotabato
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-16-0038846

₱-10,062,870.00 · FY2016

Released to Guimaras Di (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

4. Implementation

Contract Amount

₱6,216,576.27

Progress

Reported complete (DPWH)

Start Date

November 15, 2016

Target End

June 15, 2017

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.