Buildings and Facilities21FB0161

LOCAL INFRASTRUCTURE PROGRAM: CONSTRUCTION OF CAMALIG MULTI-PURPOSE BUILDING/PERMANENT EVACUATION HOLDING CENTER, CAMALIG, ALBAY

LOCAL INFRASTRUCTURE PROGRAM: CONSTRUCTION OF CAMALIG MULTI-PURPOSE BUILDING/PERMANENT EVACUATION HOLDING CENTER, CAMALIG, ALBAY is a DPWH-tracked public work in Albay 2nd DEO, Region V. Reported contract value: ₱29,045,133.23. Status: Past target date (DPWH On-Going). Contractor on record: MARCIVAN CONST AND SUPPLY. Figures trace to dpwh.

Albay 2nd DEO, Region V
Region: Region V

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱30,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Anoling-Cabangan-Salvacion Flood Control System, Camalig, Albay
GAA fiscal year
FY2021
DBM GAA source document

2. Allotment

Agency-level releases for FY2021, not tied to this contract

Albay 2nd DEO · SARO 1,294 (₱130,951,870,166.00) · NCA 1,353 (₱701,960,015,999.00)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Camalig Multi-Purpose Building

₱29,045,133.23 · MARCIVAN CONSTRUCTION AND SUPPLY

Contractor

C

48 projects · ₱618.5M total · 0 flags

Other projects by this contractor

No sat.

SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG) - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF BUSAY-BUDIAO DIKE (PHASE 2), DARAGA, ALBAY

Albay 2nd DEO, Region V

2024₱93.6M
Past target date (DPWH On-Going)
No sat.

LOCAL PROGRAM: CONCRETING/ROAD OPENING OF TAYSAN - MALANGKA - MAKRADAT - MASLOG ROAD, TAYSAN AND MASLOG, LEGASPI CITY, ALBAY

Albay 2nd DEO, Region V

2020₱60.8M
Past target date (DPWH On-Going)
No sat.

DEPED BASIC EDUCATIONAL FACILITY FUND -CONSTRUCTION OF 2-STOREY 6-CLASSROOM SCHOOL BUILDING IN ANISLAG NATIONAL HIGH SCHOOL, BARANGAY ANISLAG, DARAGA, ALBAY

Albay 2nd DEO, Region V

2024₱38.6M
Past target date (DPWH On-Going)
No sat.

DEPED BASIC EDUCATIONAL FACILITY FUND -CONSTRUCTION OF 3-STOREY 6-CLASSROOM SCHOOL BUILDING IN PURO ELEMENTARY SCHOOL, BARANGAY PURO, LEGAZPI CITY, ALBAY

Albay 2nd DEO, Region V

2024₱38.6M
Past target date (DPWH On-Going)
No sat.

19FG0071OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMDESILTING/CHANNEL IMPROVEMENT/REVETMENT AT CRISTO REY RIVER, BATO, CAMARINES SUR BATO, CAMARINES SUR

Camarines Sur 5th DEO, Region V

2019₱27.9M
Reported complete (DPWH)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODSCONST/MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS, REHAB. OF BUHI FLOOD CONTROL STRUCTURES (PHASE I), BRGY. CLARA BRGY. SAN PEDRO BRGY. STA. ELENA BRGY. SAN BUENA SECT. BUHI CAM. SUR

Camarines Sur 5th DEO, Region V

2020₱26.7M
Reported complete (DPWH)
View all 48 projects →

4. Implementation

Contract Amount

₱29,045,133.23

Progress

Past target date (DPWH On-Going)

Start Date

November 17, 2021

Target End

April 15, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.