Flood Control and Drainage19FG0071

19FG0071OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMDESILTING/CHANNEL IMPROVEMENT/REVETMENT AT CRISTO REY RIVER, BATO, CAMARINES SUR BATO, CAMARINES SUR

19FG0071OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMDESILTING/CHANNEL IMPROVEMENT/REVETMENT AT CRISTO REY RIVER, BATO, CAMARINES SUR BATO, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱27,919,295.00. Status: Reported complete (DPWH). Contractor on record: MARCIVAN CONST AND SUPPLY. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-19-0018815

₱0.00 · FY2019

Released to Division of Camarines Norte (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

48 projects · ₱618.5M total · 0 flags

Other projects by this contractor

View all 48 projects →

4. Implementation

Contract Amount

₱27,919,295.00

Progress

Reported complete (DPWH)

Start Date

July 16, 2019

Target End

January 8, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.