Construction of Slope Protection Structure22BA0027

Construction of Flood Control (Shoreline Protection) at Sitio Diptan, Barangay Sinakan, Sabtang, Batanes

Construction of Flood Control (Shoreline Protection) at Sitio Diptan, Barangay Sinakan, Sabtang, Batanes is a DPWH-tracked public work in SABTANG (BATANES), BATANES, Region II. Reported contract value: ₱4,978,478.33. Status: Reported complete (DPWH). Contractor on record: BHM CONST. Figures trace to sumbong.

SABTANG (BATANES), BATANES, Region II
Region: Region II

Money Trail

1. Appropriation

Probable match · score 100%

UACS
18001
Amount
₱6,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control (Shoreline Protection) at Sitio Diptan, Barangay Sinakan, Sabtang, Batanes
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002957

₱158,548,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002781

₱35,000,000.00 · FY2022

Source

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002809

₱3,000,000.00 · FY2022

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

206 projects · ₱6.7B total · 1 flags

Other projects by this contractor

No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) APAYAO - ILOCOS NORTE ROAD, K0619+750 - K0621+396, K0622+(-230) - K0623+771

Cordillera Administrative Region, Cordillera Administrative Region

2017₱144.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0461+854 - K0462+0032, K0464+023 - K0464+123, K0464+211 - K0464+284, K0465+157

Upper Kalinga DEO, Cordillera Administrative Region

2025₱139.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS / NEW ROADS: ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) KALINGA.

Upper Kalinga DEO, Cordillera Administrative Region

2025₱120.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONTRUCTION OF MISSING LINKS / NEW ROADS - ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) GAWAAN BRIDGE

Upper Kalinga DEO, Cordillera Administrative Region

2025₱120.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS (TERTIARY ROADS) CLAVERIA-CALANASAN-KABUGAO RD., K0695+000 - K0696+617, K0696+817 - K0698+261

Cordillera Administrative Region, Cordillera Administrative Region

2018₱118.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - PIDDIG - CARASI - CALANASAN ROAD (CALANASAN SIDE), PACKAGE 2, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2025₱113.5M
Past target date (DPWH On-Going)
View all 206 projects →

4. Implementation

Contract Amount

₱4,978,478.33

Progress

Reported complete (DPWH)

Start Date

March 21, 2022

Target End

October 31, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.