Roads17P00006

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) APAYAO - ILOCOS NORTE ROAD, K0619+750 - K0621+396, K0622+(-230) - K0623+771

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) APAYAO - ILOCOS NORTE ROAD, K0619+750 - K0621+396, K0622+(-230) - K0623+771 is a DPWH-tracked public work in Cordillera Administrative Region, Cordillera Administrative Region. Reported contract value: ₱144,749,915.62. Status: Reported complete (DPWH). Contractor on record: BHM CONST. Figures trace to dpwh.

Cordillera Administrative Region, Cordillera Administrative Region
Region: Cordillera Administrative Region

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2017 GAA. DBM GAA FY2017

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

206 projects · ₱6.7B total · 1 flags

Other projects by this contractor

No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0461+854 - K0462+0032, K0464+023 - K0464+123, K0464+211 - K0464+284, K0465+157

Upper Kalinga DEO, Cordillera Administrative Region

2025₱139.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS / NEW ROADS: ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) KALINGA.

Upper Kalinga DEO, Cordillera Administrative Region

2025₱120.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONTRUCTION OF MISSING LINKS / NEW ROADS - ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) GAWAAN BRIDGE

Upper Kalinga DEO, Cordillera Administrative Region

2025₱120.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS (TERTIARY ROADS) CLAVERIA-CALANASAN-KABUGAO RD., K0695+000 - K0696+617, K0696+817 - K0698+261

Cordillera Administrative Region, Cordillera Administrative Region

2018₱118.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - PIDDIG - CARASI - CALANASAN ROAD (CALANASAN SIDE), PACKAGE 2, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2025₱113.5M
Past target date (DPWH On-Going)
No sat.

BALANTOY-DAO-ANGAN-POSWOY-ABABA-AN ROAD IN SUPPORT OF COFFEE PROCESSING INDUSTRY, HOMESTYLES INDUSTRY (BASKETRY AND SOFTBROOM MAKING) AND FOOD PROCESSING INDUSTRY, BALBALAN, KALINGA

Cordillera Administrative Region, Cordillera Administrative Region

2023₱110.7M
Reported complete (DPWH)
View all 206 projects →

4. Implementation

Contract Amount

₱144,749,915.62

Progress

Reported complete (DPWH)

Start Date

March 16, 2017

Target End

June 18, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.