GAA 2025 OO-125PK0005

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS / NEW ROADS: ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) KALINGA.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM: CONSTRUCTION OF MISSING LINKS / NEW ROADS: ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) KALINGA. is a DPWH-tracked public work in Upper Kalinga DEO, Cordillera Administrative Region. Reported contract value: ₱120,546,739.46. Status: Past target date (DPWH On-Going). Contractor on record: BHM CONST. Figures trace to dpwh.

Upper Kalinga DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Waros Creek Phase 2, Bangad, Tinglayan, Kalinga
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Upper Kalinga DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

206 projects · ₱6.7B total · 1 flags

Other projects by this contractor

No sat.

ROAD UPGRADING (UNPAVED TO PAVED) BASED ON GRAVEL ROAD STRATEGIES, TRAFFIC BENCHMARK FOR UPGRADING TO PAVED ROAD STANDARDS (HDM-4 PROJECT ANALYSIS) APAYAO - ILOCOS NORTE ROAD, K0619+750 - K0621+396, K0622+(-230) - K0623+771

Cordillera Administrative Region, Cordillera Administrative Region

2017₱144.7M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS - TERTIARY ROADS - LUBUAGAN-BATONG BUHAY-ABRA BDRY RD - K0461+854 - K0462+0032, K0464+023 - K0464+123, K0464+211 - K0464+284, K0465+157

Upper Kalinga DEO, Cordillera Administrative Region

2025₱139.9M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM: NETWORK DEVELOPMENT PROGRAM - CONTRUCTION OF MISSING LINKS / NEW ROADS - ABRA-KALINGA-APAYAO ROAD ALONG ACIGA (PINUKPUK)-TAWANG-BUAYA-MABACA (BALBALAN SECTION, KALINGA) GAWAAN BRIDGE

Upper Kalinga DEO, Cordillera Administrative Region

2025₱120.0M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT - PAVING OF UNPAVED ROADS (TERTIARY ROADS) CLAVERIA-CALANASAN-KABUGAO RD., K0695+000 - K0696+617, K0696+817 - K0698+261

Cordillera Administrative Region, Cordillera Administrative Region

2018₱118.6M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - NETWORK DEVELOPMENT PROGRAM - CONSTRUCTION OF MISSING LINKS/ NEW ROADS - PIDDIG - CARASI - CALANASAN ROAD (CALANASAN SIDE), PACKAGE 2, APAYAO

Apayao 2nd DEO, Cordillera Administrative Region

2025₱113.5M
Past target date (DPWH On-Going)
No sat.

BALANTOY-DAO-ANGAN-POSWOY-ABABA-AN ROAD IN SUPPORT OF COFFEE PROCESSING INDUSTRY, HOMESTYLES INDUSTRY (BASKETRY AND SOFTBROOM MAKING) AND FOOD PROCESSING INDUSTRY, BALBALAN, KALINGA

Cordillera Administrative Region, Cordillera Administrative Region

2023₱110.7M
Reported complete (DPWH)
View all 206 projects →

4. Implementation

Contract Amount

₱120,546,739.46

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

February 6, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.