Roads20DK0012

ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE AND LANDSLIDES ALONG MARIKINA-INFANTA ROAD, K0119+312-K0119+382, K0121+667-K0121+684

ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE AND LANDSLIDES ALONG MARIKINA-INFANTA ROAD, K0119+312-K0119+382, K0121+667-K0121+684 is a DPWH-tracked public work in Quezon 1st DEO, Region IV-A. Reported contract value: ₱72,375,000.00. Status: Reported complete (DPWH). Contractor on record: PRECIOUS CONST. Figures trace to dpwh.

Quezon 1st DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱10,000 (shared by many projects, not this project's own line)

    Possible match · score 0.80

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20DK0012 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-05-16 → 2021-06-18

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ASSET PRESERVATION-REHABILITATION/RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE AND LANDSLIDES ALONG MARIKINA-INFANTA ROAD, K0119+312-K0119+382, K0121+667-K0121+684

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Poblacion, Polillo, Quezon
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Quezon 1st DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

Not graded

258 projects · ₱7.9B total · 0 flags

Other projects by this contractor

No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAMCONVERGENCE & SPECIAL SUPPORT PROGRAMCONSTRUCTION / IMPROVEMENT OF VARIOUS INFRASTRUCTURE IN SUPPORT OF NATIONAL SECURITYCONSTRUCTION OF 2ID PERIMETER FENCE AND GATE 1 & 2, PHASE 2,CAMP CAPINPIN, TANAY, RIZAL

Region IV-A, Region IV-A

2020₱127.6M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, SALAPAN ELEMENTARY SCHOOL, SAN JUAN CITY

Metro Manila 1st DEO, National Capital Region

2024₱117.0M
Past target date (DPWH On-Going)
No sat.

CLUSTER 01: CONSTRUCTION OF NEW PUP CAMPUS IN CALOOCAN NORTH, BARANGAY 168, CALOOCAN CITYA. CONSTRUCTION OF NEW POLYTECHNIC UNIVERSITY OF THE PHILIPPINES, BARANGAY 168, CALOOCAN CITYB. CONSTRUCTION OF ADMINISTRATIVE BUILDING - POLYTECHNIC UNIVERSITY

Metro Manila 3rd DEO, National Capital Region

2023₱116.4M
Reported complete (DPWH)
No sat.

FY 2020 DPWH INFRASTRUCTURE PROGRAM ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM NETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF MISSING LINKS/NEW ROADS, TAGAYTAY CALAMBA ROAD VIA CANLUBANG, LAGUNA SECTION, LAGUNA

Region IV-A, Region IV-A

2020₱115.4M
Reported complete (DPWH)
No sat.

CONSTRUCTION OF ALERT MULTI-PURPOSE BUILDING BRGY. MALINTA, VALENZUELA CITY

Metro Manila 3rd DEO, National Capital Region

2020₱100.6M
Reported complete (DPWH)
No sat.

CLUSTER I :A) REPAIR/REHABILITATION/IMPROVEMENT OF LUZONG-TUQUIPA ROAD, BRGYS. LUZONG AND TUQUIPA, LUBA, ABRAB) REPAIR/ REHABILITATION/ IMPROVEMENT OF SITIO CABA-GAYAMAN ROAD, BRGY GAYAMAN, LUBA, ABRAC) REPAIR/REHABILITATION/ IMPROVEMENT OF SABNANGA

Cordillera Administrative Region, Cordillera Administrative Region

2018₱100.0M
Past target date (DPWH On-Going)
View all 258 projects →

4. Implementation

Contract Amount

₱72,375,000.00

Progress

Reported complete (DPWH)

Start Date

November 27, 2020

Target End

August 13, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.