Buildings and Facilities16DE0128

CY 2016 BASIC EDUCATIONAL FACILITIES FUND (BATCH 9), CONSTRUCTION OF 4STY 20CL AT ANSELMO SANDOVAL MNHS (MABINI NHS) IN MABINI, BATANGAS

CY 2016 BASIC EDUCATIONAL FACILITIES FUND (BATCH 9), CONSTRUCTION OF 4STY 20CL AT ANSELMO SANDOVAL MNHS (MABINI NHS) IN MABINI, BATANGAS is a DPWH-tracked public work in Batangas 2nd DEO, Region IV-A. Reported contract value: ₱30,791,861.40. Status: Reported complete (DPWH). Contractor on record: VICMAR CONST INC. Figures trace to dpwh.

Batangas 2nd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Repair/Maintenance of Flood Control Project along San Juan Laiya Road, Putingbuhangin, Nagsaulay Section, Batangas City
GAA fiscal year
FY2016
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIVB-16-0035788

₱870,000.00 · FY2016

Source

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

395 projects · ₱11.0B total · 2 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF UNION - BOTONG - CONSUELO - GENERAL LUNA ROAD, SIARGAO, SURIGAO DEL NORTE

Region XIII, Region XIII

2017₱149.6M
Reported complete (DPWH)
No sat.

IMPRVT./WIDENING OF NAT'L. ROADS, ALLEN-CATARMAN ROAD (S00005SM), KO729+000-KO731+300; KO731+350-KO732+949; KO722+751-KO723+480, NORTHERN SAMAR, 1ST LD

Region VIII, Region VIII

2017₱141.7M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF TINGLOY CIRCUMFERENTIAL ROAD - PACKAGE E, SECTION II, TINGLOY, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱139.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), INTERJURISDICTIONAL ROADS AND/OR BRIDGES (ROADS THAT TRAVERSE MULTIPLE LGU JURISDICTIONS), CONSTRUCTION OF TINGLOY CIRCUMFERENTIAL ROAD - PACKAGE E, SECTION I, TINGLOY, BATANGAS

Batangas 2nd DEO, Region IV-A

2025₱139.2M
Past target date (DPWH On-Going)
No sat.

ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEMNETWORK DEVELOPMENT PROGRAM CONSTRUCTION OF BY-PASS AND DIVERSION ROADS ALAMINOS - SAN PABLO CITY BY-PASS ROAD, PACKAGE A, LAGUNA

Region IV-A, Region IV-A

2019₱130.0M
Reported complete (DPWH)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), ACCESS ROADS AND/OR BRIDGES FROM THE NATIONAL ROAD/S LEADING TO MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES, IMPROVEMENT OF ROAD, SAN PASCUAL-SAN JOSE R

Batangas 2nd DEO, Region IV-A

2023₱120.6M
Reported complete (DPWH)
View all 395 projects →

4. Implementation

Contract Amount

₱30,791,861.40

Progress

Reported complete (DPWH)

Start Date

November 14, 2016

Target End

October 24, 2017

5. Audit