Roads22IJ0093

CONCRETING OF BRGY. PANLAYAHAN TO BRGY. CAYBAGO FMR PHASE II, BRGY. PANLAYAHAN AND BRGY. CAYBAGO, CALBAYOG CITY, SAMAR

CONCRETING OF BRGY. PANLAYAHAN TO BRGY. CAYBAGO FMR PHASE II, BRGY. PANLAYAHAN AND BRGY. CAYBAGO, CALBAYOG CITY, SAMAR is a DPWH-tracked public work in Samar 1st DEO, Region VIII. Reported contract value: ₱11,846,192.40. Status: Reported complete (DPWH). Contractor on record: JFR CONST INC FORMERLY:JFR CONST. Figures trace to dpwh.

Samar 1st DEO, Region VIII
Region: Region VIII

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Sinidman River (Upstream) Phase II, Brgy. Sinidman Occidental, Calbayog City, Samar
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Agency-level releases for FY2022, not tied to this contract

Samar 1st DEO · SARO 1,577 (₱362,967,860,598.00) · NCA 828 (₱622,683,863,078.47)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

CONCRETING OF BRGY. PANLAYAHAN TO BRGY. CAYBAGO FM

₱11,295,000.00 · JFR CONSTRUCTION .

Contractor

B

307 projects · ₱6.1B total · 9 flags

4. Implementation

Contract Amount

₱11,846,192.40

Progress

Reported complete (DPWH)

Start Date

May 13, 2022

Target End

October 11, 2022

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.