Rehabilitation / Major Repair of Flood Control Structure22CD0103

Improvement of Waterways and Flood Control Structures along Angat River, Sta. 11+990 - Sta. 12+340 , Sto. Cristo, Angat, Bulacan

Improvement of Waterways and Flood Control Structures along Angat River, Sta. 11+990 - Sta. 12+340 , Sto. Cristo, Angat, Bulacan is a DPWH-tracked public work in ANGAT (BULACAN), BULACAN, Region III. Reported contract value: ₱80,794,218.29. Status: Reported complete (DPWH). Contractor on record: ST MATTHEW GEN CONTRACTOR & DEVELOPMENT CORP. Figures trace to sumbong.

ANGAT (BULACAN), BULACAN, Region III
Region: Region III

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2022 · ₱48,500

    Probable match · score 0.92

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-22-0002899 · ₱1,891,000,000

    Possible match · score 0.60

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱80,794,218 · ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT .

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2021-10-29 → 2023-10-29

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · Flood wall / dike / revetment, cost per linear meter (flood control structure)

₱230,841 per linear m= 1.1x the Region III median (n=202)

Contract cost ₱80,794,218 ÷ 350 linear m read from the DPWH title (“Sta. 11+990 - Sta. 12+340”; station range length (Sta. a+b to c+d)). National percentile: 78. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Site vs flood hazard · Project NOAH 100-year map

Outside mapped flood-hazard zones · Bulacan

Based on the coordinates published with the DPWH record and NOAH file Bulacan.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: Improvement of Waterways and Flood Control Structures along Angat River, Sta. 11+990 - Sta. 12+340 , Sto. Cristo, Angat, Bulacan

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 92%

UACS
18001
Amount
₱48,500,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Angat River, Angat, Bulacan
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002899

₱1,891,000,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002810

₱116,140,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

22CD0103 - Improvement of Waterways and Flood Cont

₱80,794,218.29 · ST. MATTHEW GEN. CONTRACTOR & DEVELOPMENT .

Contractor

B

61 projects · ₱4.8B total · 15 flags

4. Implementation

Contract Amount

₱80,794,218.29

Progress

Reported complete (DPWH)

Start Date

March 30, 2022

Target End

February 11, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.