Roads23JF0006

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - IPIL - LILOY - SINDANGAN RD. K2000 + 560 - K2000 +860, K2004 + 095 - K2004 + 220, K2004 +560 - K2004 + 600, K2004 + 640 - K2004 + 650, K2005 + 000 - K2005 +

REHABILITATION/ RECONSTRUCTION OF ROADS WITH SLIPS SLOPE COLLAPSE, AND LANDSLIDE - PRIMARY ROADS - IPIL - LILOY - SINDANGAN RD. K2000 + 560 - K2000 +860, K2004 + 095 - K2004 + 220, K2004 +560 - K2004 + 600, K2004 + 640 - K2004 + 650, K2005 + 000 - K2005 + is a DPWH-tracked public work in Zamboanga Sibugay 2nd DEO, Region IX. Reported contract value: ₱40,044,414.90. Status: Reported complete (DPWH). Contractor on record: LAKEWOOD CONST CO. Figures trace to dpwh.

Zamboanga Sibugay 2nd DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (revetment wall) along Sibuguey River (upstream), Sta. 0+000.00 - Sta. 0+417.00, Barangay Sampoli A, Diplahan, Zamboanga Sibugay (Package 2)
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Zamboanga Sibugay 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

98 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱40,044,414.90

Progress

Reported complete (DPWH)

Start Date

February 20, 2023

Target End

January 10, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.