Roads22JI0003

ROAD WIDENING -TERTIARY ROADS - JCT IMELDA-ALICIA RD - K1765 + 619.00 - K1766 + 525.00, K1768 + 066.00 - K1769 + 170.00

ROAD WIDENING -TERTIARY ROADS - JCT IMELDA-ALICIA RD - K1765 + 619.00 - K1766 + 525.00, K1768 + 066.00 - K1769 + 170.00 is a DPWH-tracked public work in Zamboanga Sibugay 1st DEO, Region IX. Reported contract value: ₱57,824,811.48. Status: Reported complete (DPWH). Contractor on record: LAKEWOOD CONST CO. Figures trace to dpwh.

Zamboanga Sibugay 1st DEO, Region IX
Region: Region IX

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure (Revetment Wall) along Sibuguey River, Barangay San Jose, Imelda, Zamboanga Sibugay
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

NCA NCA-ROXI-22-0007894

₱5,000.00 · FY2022

Released to Division of Davao del Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM NCA listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

C

98 projects · ₱1.6B total · 0 flags

4. Implementation

Contract Amount

₱57,824,811.48

Progress

Reported complete (DPWH)

Start Date

April 4, 2022

Target End

January 17, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.