Construction of Flood Mitigation Structure24JF0007

Construction of Flood Control Structure along Tupilac River (Phase IV), RT Lim, Zamboanga Sibugay

Construction of Flood Control Structure along Tupilac River (Phase IV), RT Lim, Zamboanga Sibugay is a DPWH-tracked public work in IPIL (CAPITAL) (ZAMBOANGA SIBUGAY), ZAMBOANGA SIBUGAY, Region IX. Reported contract value: ₱57,749,526.89. Status: Reported complete (DPWH). Contractor on record: LAKEWOOD CONST CO. Figures trace to sumbong.

IPIL (CAPITAL) (ZAMBOANGA SIBUGAY), ZAMBOANGA SIBUGAY, Region IX
Region: Region IX

Money Trail

1. Appropriation

Probable match · score 91%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure along Sibuguey River, Barangay Lumpanac, Imelda, Zamboanga Sibugay
GAA fiscal year
FY2024
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0007645

₱1,334,511.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0018043

₱1,284,970.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0001900

₱946,848.00 · FY2024

Source

Office-level release, not tied to this specific contract

SARO SARO-ROIX-24-0007646

₱123,222.00 · FY2024

Source

3. Procurement & Award

4. Implementation

Contract Amount

₱57,749,526.89

Progress

Reported complete (DPWH)

Start Date

March 12, 2024

Target End

November 11, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.