Roads20DM0018

ASSET PRESERVATION: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0314+860 - K0315+293, K0315+486 - K0316+900, K0359+940 - K0363+313, SAN FRANCISCO - SAN ANDRES, QUEZON

ASSET PRESERVATION: CONSTRUCTION/UPGRADING/REHABILITATION OF DRAINAGE ALONG NATIONAL ROADS - SECONDARY ROADS - SN FRANCISCO-SN ANDRES-SN NARCISO RD - K0314+860 - K0315+293, K0315+486 - K0316+900, K0359+940 - K0363+313, SAN FRANCISCO - SAN ANDRES, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱64,900,110.00. Status: Reported complete (DPWH). Contractor on record: WAYCON BUILDERS AND CONST SUPPLY CORP FOR:WAYCON BUILDERS. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A
Region: Region IV-A

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Poblacion, Polillo, Quezon
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Quezon 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱64,900,110.00

Progress

Reported complete (DPWH)

Start Date

February 24, 2020

Target End

January 18, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.