Roads19GG0023

RECONSTRUCTION TO CONCRETE PAVEMENT OF PASSI - SAN ENRIQUE - GARRITA ROAD, K0050 + 000 - K0050 + 189, K0050 + (-394) - K0050 + (-94), K0056 + 050 - K0056 + 860, K0061 + 200 - K0061 + 250, K0061 + 266 - K 0061 + 287, K0059 + 757 - K0059 + 809

RECONSTRUCTION TO CONCRETE PAVEMENT OF PASSI - SAN ENRIQUE - GARRITA ROAD, K0050 + 000 - K0050 + 189, K0050 + (-394) - K0050 + (-94), K0056 + 050 - K0056 + 860, K0061 + 200 - K0061 + 250, K0061 + 266 - K 0061 + 287, K0059 + 757 - K0059 + 809 is a DPWH-tracked public work in Iloilo 2nd DEO, Region VI. Reported contract value: ₱26,814,688.73. Status: Reported complete (DPWH). Contractor on record: LVRO CONST. Figures trace to dpwh.

Iloilo 2nd DEO, Region VI
Region: Region VI

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-19-0009858

₱304,118.00 · FY2019

Released to 000000 - Metals Industry Research Dan and Development Center (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱26,814,688.73

Progress

Reported complete (DPWH)

Start Date

July 11, 2019

Target End

January 12, 2020

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.