Flood Control and Drainage18KH0040

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF CAGAYAN DE ORO CITY RIVER BASIN FLOOD CONTROL PROJECT BINONOAN CREEK (WITH SLUICE WAY AND GATE), CAGAYAN DE ORO CITY

CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF CAGAYAN DE ORO CITY RIVER BASIN FLOOD CONTROL PROJECT BINONOAN CREEK (WITH SLUICE WAY AND GATE), CAGAYAN DE ORO CITY is a DPWH-tracked public work in Cagayan de Oro City 1st DEO, Region X. Reported contract value: ₱45,301,690.96. Status: Reported complete (DPWH). Contractor on record: C'ZARLES CONST. Figures trace to dpwh.

Cagayan de Oro City 1st DEO, Region X
Region: Region X

Follow the peso

3 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    FY2018 · ₱50,000

    Probable match · score 0.93

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-18-0026851 · ₱2,563,405 · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱45,301,691 · C'ZARLES CONSTRUCTION & SUPPLY

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · imagery 2018-02-23 → 2020-03-11

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Medium flood hazard · Misamis Oriental

Based on the coordinates published with the DPWH record and NOAH file MisamisOriental.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS: CONSTRUCTION OF CAGAYAN DE ORO CITY RIVER BASIN FLOOD CONTROL PROJECT BINONOAN CREEK (WITH SLUICE WAY AND GATE), CAGAYAN DE ORO CITY

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Probable match · score 93%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Cagayan de Oro City River Basin Flood Control Project Binonoan Creek (with Sluice Way and Gate), Cagayan de Oro City
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-18-0026851

₱2,563,405.00 · FY2018

Released to Central Office (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Contract ID 18KH0040

₱45,301,690.96 · C'ZARLES CONSTRUCTION & SUPPLY

Award / contract ref: Contract ID: 18KH0040

Contractor

173 projects · ₱7.0B total · 0 flags

4. Implementation

Contract Amount

₱45,301,690.96

Progress

Reported complete (DPWH)

Start Date

March 22, 2018

Target End

November 23, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.