Buildings and Facilities19A00135

STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS - REGION I, CONSTRUCTION OF EVACUATION CENTERS - REGION I, BRGY. LAUREN, UMINGAN, PANGASINAN

STRUCTURAL IMPROVEMENT OF PUBLIC BUILDINGS AND CONSTRUCTION OF EVACUATION CENTERS - REGION I, CONSTRUCTION OF EVACUATION CENTERS - REGION I, BRGY. LAUREN, UMINGAN, PANGASINAN is a DPWH-tracked public work in Region I, Region I. Reported contract value: ₱34,151,171.81. Status: Reported complete (DPWH). Contractor on record: AMP 723 CONST CORP FORMERLY: A M P CONST. Figures trace to dpwh.

Region I, Region I
Region: Region I

Money Trail

1. Appropriation

No matching GAA line found for this project in the FY2019 GAA. DBM GAA FY2019

2. Allotment

No matching SARO/NCA release found for this project. Source: DBM SARO/NCA listings.

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF THE EVACUATION AND CONVENTION CENTER, SAN LEONARDO, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, V. LUNA HOSPITAL COMPOUND, QUEZON CITY

Quezon City 2nd DEO, National Capital Region

2025₱145.5M
Ongoing (DPWH-reported)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BENAY - BARANGAY PALABOT

Nueva Vizcaya 2nd DEO, Region II

2025₱142.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, BARANGAY SAPANG. JAEN, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2025₱120.0M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BAGUMBAYAN FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BARANGAY BAGUMBAYAN,

Nueva Vizcaya 2nd DEO, Region II

2025₱102.1M
Past target date (DPWH On-Going)

Improvement of River Channel along Talavera River (Brgy. Cabubulaonan), Talavera, Nueva Ecija

TALAVERA (NUEVA ECIJA), NUEVA ECIJA, Region III

2023₱99.0M
Reported complete (DPWH)
View all 519 projects →

4. Implementation

Contract Amount

₱34,151,171.81

Progress

Reported complete (DPWH)

Start Date

September 10, 2019

Target End

December 20, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.