Buildings and Facilities25OG0133

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, V. LUNA HOSPITAL COMPOUND, QUEZON CITY

CONSTRUCTION OF MULTI-PURPOSE BUILDING, PHASE 2, V. LUNA HOSPITAL COMPOUND, QUEZON CITY is a DPWH-tracked public work in Quezon City 2nd DEO, National Capital Region. Reported contract value: ₱145,521,150.81. Status: Ongoing (DPWH-reported) (Not Yet Started (DPWH-reported)). Contractor on record: AMP 723 CONST CORP FORMERLY: A M P CONST. Figures trace to dpwh.

Quezon City 2nd DEO, National Capital Region
Region: National Capital Region

Money Trail

1. Appropriation

Probable match · score 86%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structure along Marikina River, Phase 2, Barangay Bagumbayan, Quezon City
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Quezon City 2nd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

519 projects · ₱11.9B total · 7 flags

Other projects by this contractor

No sat.

BASIC INFRASTRUCTURE PROGRAM (BIP) - EVACUATION CENTERS / QUARANTINE FACILITIES / PUBLIC HEALTH FACILITIES - CONSTRUCTION OF THE EVACUATION AND CONVENTION CENTER, SAN LEONARDO, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2024₱192.9M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM - BASIC INFRASTRUCTURE PROGRAM (BIP) - BIP - FLOOD MITIGATION STRUCTURES PROTECTING MAJOR/ STRATEGIC PUBLIC BUILDINGS/ FACILITIES - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BENAY - BARANGAY PALABOT

Nueva Vizcaya 2nd DEO, Region II

2025₱142.6M
Past target date (DPWH On-Going)
No sat.

FLOOD MANAGEMENT PROGRAM -CONSTRUCTION/REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS - CONSTRUCTION OF FLOOD CONTROL STRUCTURE ALONG PAMPANGA RIVER, BARANGAY SAPANG. JAEN, NUEVA ECIJA

Nueva Ecija 2nd DEO, Region III

2025₱120.0M
Past target date (DPWH On-Going)
No sat.

OO2: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS - FLOOD MANAGEMENT PROGRAM - CONSTRUCTION/ MAINTENANCE OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEMS - CONSTRUCTION OF BAGUMBAYAN FLOOD CONTROL STRUCTURE ALONG BENAY RIVER, BARANGAY BAGUMBAYAN,

Nueva Vizcaya 2nd DEO, Region II

2025₱102.1M
Past target date (DPWH On-Going)

Improvement of River Channel along Talavera River (Brgy. Cabubulaonan), Talavera, Nueva Ecija

TALAVERA (NUEVA ECIJA), NUEVA ECIJA, Region III

2023₱99.0M
Reported complete (DPWH)

Construction of Slope Protection along Talavera River, Brgy. San Jose, Licab, Nueva Ecija

LICAB (NUEVA ECIJA), NUEVA ECIJA, Region III

2022₱96.5M
Reported complete (DPWH)
View all 519 projects →

4. Implementation

Contract Amount

₱145,521,150.81

Progress

Not Yet Started (DPWH-reported)

Start Date

Data not yet available

Target End

March 23, 2026

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.