Bridges20FE0115

LP:LOCAL ROADS AND BRIDGES-LOCAL BRIDGES-LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION/REHABILITATION OF BRIDGE, BRGY. MARANGI, SAN FERNANDO, CAMARINES SUR

LP:LOCAL ROADS AND BRIDGES-LOCAL BRIDGES-LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION/REHABILITATION OF BRIDGE, BRGY. MARANGI, SAN FERNANDO, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 2nd DEO, Region V. Reported contract value: ₱2,425,400.00. Status: Reported complete (DPWH). Contractor on record: JMLD CONST. Figures trace to dpwh.

Camarines Sur 2nd DEO, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.85

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20FE0115 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2020-01-11 → 2020-01-11

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: LP:LOCAL ROADS AND BRIDGES-LOCAL BRIDGES-LOCAL INFRASTRUCTURE PROGRAM-CONSTRUCTION/REHABILITATION OF BRIDGE, BRGY. MARANGI, SAN FERNANDO, CAMARINES SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 85%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Mitigation Structures/Facilities along Libmanan River at Brgy. Sibujo, Libmanan, Camarines Sur
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Camarines Sur 2nd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

113 projects · ₱1.9B total · 0 flags

Other projects by this contractor

No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF FLOOD CONTROL STRUCT. ALONG ANYATAM-MAPANIQUE CREEK, PHASE 5, SAN ILDEFON

Region III, Region III

2024₱133.0M
Ongoing (DPWH-reported)
No sat.

CONVERGENCE & SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJ. ALLEVIATING GAPS (SIPAG)-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS./FACILITIES-CONST. OF FLOOD CTRL. STRUCTURE ALONG ANYATAM-MAPANIQUE CREEK,PHASE 8,SAN ILDEFONSO,BUL.

Region III, Region III

2024₱114.1M
Ongoing (DPWH-reported)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-SIPAG- FLOOD MITIGATION STRUCTS. PRTOTECTING MAJOR/STRAT. PUBLIC BLDGS./FACILITIES-CONST. OF FLOOD MITIGATION STRUCT. ALONG SAN MIGUEL RIVER, SEGMENT B (SIOJO ST. SEC.)

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

CONVERG. AND SPL. SUPPORT PROG.-SUST. INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-FLOOD MITIGATION STRUCT. PROTECTING MAJ./STRAT. PUBLIC BLDGS./FACS.-CONST. OF RIVERBANK PROTECTION STRUCT. ALONG MALANGAAN RIVER(DOWNSTREAM), BRGY. CAMACHILE, DONA REMEDIO

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

CONVERG. AND SPL. SUPPORT PROG.-SUST. INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-SIPAG-FLOOD MITIGATION STRUCT. PROTECTING MAJ./STRAT. PUBLIC BLDGS./FACS.-CONST. OF RIVERBANK PROTECTION STRUCT. ALONG MALANGAAN RIVER(UPSTREAM), BRGY. CAMACHILE, DONA REMEDIOS

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
No sat.

CONVERGE. AND SPECIAL SUPPORT PROG.-SUSTAINABLE INFRA. PROJS. ALLEVIATING GAPS (SIPAG)-SIPAG-FLOOD MITIGATION STRUCTS .PROTECTING MAJOR/STRATEGIC PUBLIC BLDGS./ FACILITIES-CONST. OF FLOOD MITIGATION STRUCT. ALONG SAN MIGUEL RIVER, SEG. A (SIOJO ST. SEC.),

Bulacan 3rd DEO, Region III

2025₱95.1M
Past target date (DPWH On-Going)
View all 113 projects →

4. Implementation

Contract Amount

₱2,425,400.00

Progress

Reported complete (DPWH)

Start Date

October 7, 2020

Target End

February 9, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.