ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, TERTIARY ROADS, LIPA CITY-ALAMINOS RD

ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, TERTIARY ROADS, LIPA CITY-ALAMINOS RD is a DPWH-tracked public work in Batangas 3rd DEO, Region IV-A. Reported contract value: ₱43,114,331.47. Status: Reported complete (DPWH). Contractor on record: N D M SANCHEZ BUILDERS. Figures trace to dpwh.

Batangas 3rd DEO, Region IV-A
Region: Region IV-A

Follow the peso

1 of 5 steps linked to this project, 1 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2020 · ₱2,000 (shared by many projects, not this project's own line)

    Possible match · score 0.82

    DBM GAA source ↗
  2. 2. SARO / NCA release

    No SARO/NCA found for this office and year. DBM publishes releases by agency and office, rarely by project.

  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 20DC0003 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2015-03-08 → 2015-03-08

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, NETWORK DEVELOPMENT PROGRAM, ROAD WIDENING, TERTIARY ROADS, LIPA CITY-ALAMINOS RD

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 82%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Systems, Alitagtag, Batangas
GAA fiscal year
FY2020
DBM GAA source document

2. Allotment

Agency-level releases for FY2020, not tied to this contract

Batangas 3rd DEO · SARO 1,970 (₱160,521,624,356.00) · NCA 998 (₱407,918,568,220.27)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

188 projects · ₱4.0B total · 0 flags

Other projects by this contractor

No sat.

CONSTRUCTION OF MULTI-PURPOSE BUILDING, ROSARIO, BATANGAS

Region IV-A, Region IV-A

2025₱194.1M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. CASTILLO, PADRE GARCIA, BATANGAS

Batangas 4th DEO, Region IV-A

2024₱115.2M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), COASTAL ROADS TO AUGMENT RESILIENCY OF COASTAL COMMUNITIES, IMPROVEMENT OF BAUAN - MABINI CIRCUMFERENTIAL ROAD, BARANGAY SAN JUAN, MAINAGA SECTION, MABI

Batangas 2nd DEO, Region IV-A

2025₱114.6M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING, BRGY. SAN SEBASTIAN, MATAAS NA KAHOY, BATANGAS

Batangas 3rd DEO, Region IV-A

2023₱99.0M
Past target date (DPWH On-Going)
No sat.

CSSP - BASIC INFRASTRUCTURE PROGRAM (BIP) - MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES - CONSTRUCTION OF MULTI PURPOSE BUILDING (PAMANTASAN NG LUNGSOD NG SAN PABLO), BRGY SAN JOSE, SAN PABLO CITY, LAGUNA

Laguna 3rd DEO, Region IV-A

2025₱96.5M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM, SUSTAINABLE INFRASTRUCTURE PROJECTS ALLEVIATING GAPS (SIPAG), MULTI-PURPOSE BUILDINGS/ FACILITIES TO SUPPORT SOCIAL SERVICES, CONSTRUCTION OF MULTI-PURPOSE BUILDING (PUBLIC MARKET), ROSARIO, BATANGAS, PHASE 2

Batangas 4th DEO, Region IV-A

2023₱93.6M
Reported complete (DPWH)
View all 188 projects →

4. Implementation

Contract Amount

₱43,114,331.47

Progress

Reported complete (DPWH)

Start Date

November 25, 2020

Target End

July 22, 2021

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.

Connected records

Where this project sits

Place (PSGC)
Region IV-A (CALABARZON)BatangasCity of Sto. TomasSanta Cruz
Storms whose wind field reached it
None on record (IBTrACS tracks).
Hazard exposure
Flood (100-yr rain)Details in Hazard context above.Full hazard check →
El Niño outlook (province)
No PAGASA drought or dry flag for this province.El Niño readiness →

Exposure to a storm, hazard or drought outlook is context, not a finding about the project.