Buildings and Facilities23IA0133

CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY ONE (1) CLASSROOM SCHOOL BUILDING, UNGALE II ELEMENTARY SCHOOL, BARANGAY UNGALE, KAWAYAN, BILIRAN

CONSTRUCTION OF ONE (1) UNIT, ONE (1) STOREY ONE (1) CLASSROOM SCHOOL BUILDING, UNGALE II ELEMENTARY SCHOOL, BARANGAY UNGALE, KAWAYAN, BILIRAN is a DPWH-tracked public work in Biliran DEO, Region VIII. Reported contract value: ₱2,953,750.90. Status: Reported complete (100% progress, DPWH status On-Going). Contractor on record: LCTING CONST AND DEVELOPMENT CORP FORMERLY: L C TING CONST. Figures trace to dpwh.

Biliran DEO, Region VIII
Region: Region VIII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱10,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Sitio Buri, Barangay Ungale, Kawayan, Biliran
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Biliran DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

304 projects · ₱17.1B total · 2 flags

4. Implementation

Contract Amount

₱2,953,750.90

Progress

Reported complete (100% progress, DPWH status On-Going)

Start Date

August 21, 2023

Target End

November 3, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.