Roads23PB0013

NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - TERTIARY ROADS, APAYAO-CAGAYAN ROAD (ILI-GUINAMGAMMAN-RIZAL ROAD) - (S00694LZ) CHAINAGE 0 - CHAINAGE 3027

NETWORK DEVELOPMENT PROGRAM - PAVING OF UNPAVED ROADS - TERTIARY ROADS, APAYAO-CAGAYAN ROAD (ILI-GUINAMGAMMAN-RIZAL ROAD) - (S00694LZ) CHAINAGE 0 - CHAINAGE 3027 is a DPWH-tracked public work in Apayao 1st DEO, Cordillera Administrative Region. Reported contract value: ₱72,375,000.00. Status: Reported complete (DPWH). Contractor on record: TAGEL CORP. Figures trace to dpwh.

Apayao 1st DEO, Cordillera Administrative Region
Region: Cordillera Administrative Region

Money Trail

1. Appropriation

Possible match · score 80%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Madduang River Flood Control along Apayao-Abulug River Basin, Sta. 88 + 535 - Sta. 88 + 680 (L/S), Sta. 89 + 133 - Sta. 89 + 633 (R/S), Madduang, Kabugao, Apayao
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Apayao 1st DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

62 projects · ₱2.1B total · 0 flags

Other projects by this contractor

No sat.

LOCAL PROGRAM: LOCAL INFRASTRUCTURE PROGRAM - BUILDINGS AND OTHER STRUCTURES - MULTIPURPOSE/ FACILITIES - CONSTRUCTION/ REHABILITATION OF MULTI-PURPOSE BUILDING (BENGUET SPORTS COMPLEX AND FACILITIES) AT BARANGAY WANGAL, LA TRINIDAD, BENGUET

Cordillera Administrative Region, Cordillera Administrative Region

2021₱163.3M
Reported complete (DPWH)

Construction of Flood Control Structure along Apayao River Basin, Tanglagan Section, Calanasan, Apayao

CALANASAN (BAYAG) (APAYAO), APAYAO, Cordillera Administrative Region

2023₱96.5M
Reported complete (DPWH)

Construction of Apayao-Abulug River Basin Flood Control Structure, Capannikian Section, Sta. 34 + 440 - Sta. 34 + 995 (R/S), Pudtol, Apayao

PUDTOL (APAYAO), APAYAO, Cordillera Administrative Region

2023₱96.5M
Reported complete (DPWH)
No sat.

ORGANIZATIONAL OUTCOME 1 : ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM - ASSET PRESERVATION PROGRAM - REHABILITATION/ RECONSTRUCTION/ UPGRADING OF DAMAGED PAVED ROADS - TERTIARY ROADS - AYAGA-STA. MARCELA-FLORA-LASAM RD - K0679 + 000 - K0680 + 500

Apayao 2nd DEO, Cordillera Administrative Region

2024₱94.5M
Past target date (DPWH On-Going)
No sat.

ORGANIZATIONAL OUTCOME 2 : PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS, FLOOD MANAGEMENT PROGRAM- CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF APAYAO RIVER FLOOD CONTROL

Apayao 1st DEO, Cordillera Administrative Region

2024₱93.6M
Reported complete (100% progress, DPWH status On-Going)
No sat.

002: PROTECT LIVES AND PROPERTIES AGAINST MAJOR FLOODS CONSTRUCTION/ REHABILITATION OF FLOOD MITIGATION FACILITIES WITHIN MAJOR RIVER BASINS AND PRINCIPAL RIVERS, CONSTRUCTION OF KARAGAWAN RIVER FLOOD CONTROL, STA. 81+404 - STA. 82+456 (L/S), KARAGAWAN, K

Apayao 1st DEO, Cordillera Administrative Region

2024₱93.6M
Reported complete (100% progress, DPWH status On-Going)
View all 62 projects →

4. Implementation

Contract Amount

₱72,375,000.00

Progress

Reported complete (DPWH)

Start Date

April 6, 2023

Target End

January 1, 2024

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.