Construction of Flood Mitigation Structure22GI0014

Construction of Aganan Flood Control Project (Jaro-Aganan River), Brgy. 5 to Brgy. Sto. Niño, San Miguel, Iloilo

Construction of Aganan Flood Control Project (Jaro-Aganan River), Brgy. 5 to Brgy. Sto. Niño, San Miguel, Iloilo is a DPWH-tracked public work in SAN MIGUEL (ILOILO), ILOILO, Region VI. Reported contract value: ₱96,499,992.73. Status: Reported complete (DPWH). Contractor on record: F GURREA CONST INC / GOOD FORTUNE INTERNATIONAL INC. Figures trace to sumbong.

SAN MIGUEL (ILOILO), ILOILO, Region VI
Region: Region VI

Money Trail

1. Appropriation

Probable match · score 90%

UACS
18001
Amount
₱40,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Brgy. Barrido, Ajuy, Iloilo
GAA fiscal year
FY2022
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0002723

₱407,950,000.00 · FY2022

DBM SARO listing (source)

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-22-0001778

₱30,000,000.00 · FY2022

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

1 projects · ₱96.5M total · 0 flags

4. Implementation

Contract Amount

₱96,499,992.73

Progress

Reported complete (DPWH)

Start Date

February 21, 2022

Target End

June 4, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.