Buildings and Facilities17DM0165No coordinates published by DPWH

CONSTRUCTION OF TWO-STOREY FOUR-CLASSROOM SCHOOL BUILDING AT HAGONGHONG INTEGRATED HS, BUENAVISTA, QUEZON

CONSTRUCTION OF TWO-STOREY FOUR-CLASSROOM SCHOOL BUILDING AT HAGONGHONG INTEGRATED HS, BUENAVISTA, QUEZON is a DPWH-tracked public work in Quezon 3rd DEO, Region IV-A. Reported contract value: ₱9,718,761.98. Status: Reported complete (DPWH). Contractor on record: QUEZON VICTORY LUMBER AND GEN CONTRACTOR. Figures trace to dpwh.

Quezon 3rd DEO, Region IV-A

DPWH did not publish coordinates for this project, so it cannot be placed on the map or checked with satellite images.

Region: Region IV-A

No before/after satellite images: DPWH has not published map coordinates for this project, so there is no location to image.

Follow the peso

2 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱50,000 (shared by many projects, not this project's own line)

    Possible match · score 0.83

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-E-17-0021010 · ₱300,000,000 · release to the district office, not itemized per project

    Possible match · score 0.61

    DBM release source ↗
  3. 3. PhilGEPS award

    ₱9,718,762 · QUEZON VICTORY LUMBER AND GENERAL CONTRACTOR

    Confirmed (exact contract ID) · score 1.00

    PhilGEPS source ↗
  4. 4. DPWH progress + satellite

    100% reported · no satellite pair yet

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Unit-cost benchmark · School building, cost per classroom (new school building)

₱2,429,690 per classroom= 1.1x the Region IV-A median (n=665)

Contract cost ₱9,718,762 ÷ 4 classroom read from the DPWH title (“FOUR-CLASSROOM”; classroom count in title). National percentile: 78. Higher unit cost can have legitimate causes (terrain, design, scope not stated in the title); this is a comparison, not a finding. Methodology

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF TWO-STOREY FOUR-CLASSROOM SCHOOL BUILDING AT HAGONGHONG INTEGRATED HS, BUENAVISTA, QUEZON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱50,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures along Hingoso River, San Isidro Ibaba-San Vicente Section, General Luna, Quezon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-E-17-0021010

₱300,000,000.00 · FY2017

Released to Regional Field Unit - V (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

Confirmed (exact contract ID) · 100%

Construction of Two-Storey Four-Classroom School B

₱9,718,761.98 · QUEZON VICTORY LUMBER AND GENERAL CONTRACTOR

Award / contract ref: 17DM0165

4. Implementation

Contract Amount

₱9,718,761.98

Progress

Reported complete (DPWH)

Start Date

December 18, 2017

Target End

July 15, 2018

5. Audit