Flood Control and Drainage18FG0005

CONSTRUCTION OF LINE CANAL, ZONE 2 & 3, BARGY. STO. DOMINGO, BULA, CAMARINES SUR

CONSTRUCTION OF LINE CANAL, ZONE 2 & 3, BARGY. STO. DOMINGO, BULA, CAMARINES SUR is a DPWH-tracked public work in Camarines Sur 5th DEO, Region V. Reported contract value: ₱1,877,434.58. Status: Reported complete (DPWH). Contractor on record: JVM CEGUERA CONST. Figures trace to dpwh.

Camarines Sur 5th DEO, Region V
Region: Region V

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2018 · ₱2,000 (shared by many projects, not this project's own line)

    Possible match · score 0.84

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-ROV-18-0032622 · · release to the district office, not itemized per project

    Possible match · score 0.81

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 18FG0005 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2017-05-08 → 2022-12-06

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Site vs flood hazard · Project NOAH 100-year map

Low flood hazard · Camarines Sur

Based on the coordinates published with the DPWH record and NOAH file CamarinesSur.zip. Pins are sometimes placed at the town center rather than the site. NOAH data (ODbL) · Need vs spending by province

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF LINE CANAL, ZONE 2 & 3, BARGY. STO. DOMINGO, BULA, CAMARINES SUR

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 84%

UACS
18001
Amount
₱2,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control System, Brgy. North Centro Sipocot, Camarines Sur
GAA fiscal year
FY2018
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-ROV-18-0032622

₱0.00 · FY2018

Released to Division of Camarines Sur (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱1,877,434.58

Progress

Reported complete (DPWH)

Start Date

March 2, 2018

Target End

May 24, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.