CONSTRUCTION OF 1 UNIT, 2 STY - 6 CL SCHOOL BUILDING, KITUBO NHS, KITAOTAO, BUKIDNON

CONSTRUCTION OF 1 UNIT, 2 STY - 6 CL SCHOOL BUILDING, KITUBO NHS, KITAOTAO, BUKIDNON is a DPWH-tracked public work in Bukidnon 2nd DEO, Region X. Reported contract value: ₱12,512,227.23. Status: Reported complete (DPWH). Contractor on record: HERBANA BUILDERS AND SUPPLY. Figures trace to dpwh.

Bukidnon 2nd DEO, Region X
Region: Region X

Follow the peso

1 of 5 steps linked to this project, 2 at office level only. Links are automated matches unless marked confirmed.

  1. 1. GAA budget line

    District-office budget line, FY2017 · ₱33,000 (shared by many projects, not this project's own line)

    Possible match · score 0.81

    DBM GAA source ↗
  2. 2. SARO / NCA release

    SARO SARO-BMB-A-17-0018299 · ₱289,925 · release to the district office, not itemized per project

    Possible match · score 0.58

    DBM release source ↗
  3. 3. PhilGEPS award

    Not found in PhilGEPS by contract ID 17KB0144 or title. The open PhilGEPS mirror does not include every DPWH notice.

  4. 4. DPWH progress + satellite

    100% reported · imagery 2016-10-07 → 2020-10-23

    Same record (DPWH contract ID)

    DPWH Transparency Portal source ↗
  5. 5. COA audit finding

    No COA finding names this project. COA audits DPWH by office each year; project-level findings are only linked when the report names the contract.

Been to this site?

Share a photo of what is there today. Faces and vehicle plates are blurred automatically, all photo metadata except the date and location is removed, and nothing is published until a moderator approves it.

Watch this project

Get a weekly email when this project changes: progress, new linked records or newly published anomaly flags.

Share card: CONSTRUCTION OF 1 UNIT, 2 STY - 6 CL SCHOOL BUILDING, KITUBO NHS, KITAOTAO, BUKIDNON

Share this page

The card shows the public record facts and a QR code back to this page.

FacebookDownload image

Money Trail

1. Appropriation

Possible match · score 81%

UACS
18001
Amount
₱33,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Rehabilitation of Flood Control Structure along Misamis Oriental Bukidnon Agusan Road with Slope Protection, Malitbog, Bukidnon
GAA fiscal year
FY2017
DBM GAA source document

2. Allotment

Office-level release, not tied to this specific contract

SARO SARO-BMB-A-17-0018299

₱289,925.00 · FY2017

Released to Regional Office - IV (office-level, not project-specific). This SARO/NCA funds the office's programme; DBM listings do not tie it to this contract.

DBM SARO listing (source)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

B

31 projects · ₱726.9M total · 0 flags

4. Implementation

Contract Amount

₱12,512,227.23

Progress

Reported complete (DPWH)

Start Date

March 18, 2018

Target End

September 3, 2018

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.