Bridges23CD0114

ORGANIZATIONAL OUTCOME 1 BRIDGE PROGRAM REPLACEMENT OF PERMANENT WEAK BRIDGES - C. DE LEON BR. 1 (B01679LZ) ALONG DAANG MAHARLIKA (LZ)

ORGANIZATIONAL OUTCOME 1 BRIDGE PROGRAM REPLACEMENT OF PERMANENT WEAK BRIDGES - C. DE LEON BR. 1 (B01679LZ) ALONG DAANG MAHARLIKA (LZ) is a DPWH-tracked public work in Bulacan 2nd DEO, Region III. Reported contract value: ₱20,253,069.26. Status: Reported complete (DPWH). Contractor on record: ADSL CONST. Figures trace to dpwh.

Bulacan 2nd DEO, Region III
Region: Region III

Money Trail

1. Appropriation

Possible match · score 83%

UACS
18001
Amount
₱20,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structures, Maasim River along Maharlika Highway Phase 1, San Rafael Section (TP), Maasim, San Rafael, Bulacan
GAA fiscal year
FY2023
DBM GAA source document

2. Allotment

Agency-level releases for FY2023, not tied to this contract

Bulacan 2nd DEO · SARO 16 (₱22,616,681,592.00) · NCA 0 (₱0.00)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

Contractor

F

101 projects · ₱5.0B total · 0 flags

Other projects by this contractor

No sat.

CONST./MAINT. OF FLOOD MITIGATION STRUCTURES AND DRAINAGE SYSTEM- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, BRGY. MULAWIN-BRGY. GENERAL ESCO, NAUJAN, OR. MINDORO

Region IV-B, Region IV-B

2025₱137.9M
Past target date (DPWH On-Going)
No sat.

CONST./MAINT. OF FLOOD MITIGATION SRTRUCTURES AND DRAINAGE SYSTEM- CONST. OF ROAD DIKE ALONG BUCAYAO RIVER, PJHASE 2, BRGY. MULAWIMN, NAUJAN, ORINTAL MINORO

Region IV-B, Region IV-B

2025₱137.9M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- TERTIARY ROADS- ASPHALT OVERLAY INCLUDING ROAD SAFETY DEVICES ALONG SN MIGUEL- SIBUL RD NETWORK, PHASE 2, SAN MIGUEL, BULACAN

Bulacan 3rd DEO, Region III

2025₱133.7M
Past target date (DPWH On-Going)
No sat.

ASSET PRESERVATION PROGRAM- PREVENTIVE MAINTENANCE- TERTIARY ROADS- ASPHALT OVERLAY INCLUDING ROAD SAFETY DEVICES ALONG SN MIGUEL- SIBUL RD NETWORK, PHASE 1, SAN MIGUEL, BULACAN

Bulacan 3rd DEO, Region III

2025₱133.7M
Past target date (DPWH On-Going)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF FLOOD CONTROL STRUCT. ALONG ANYATAM-MAPANIQUE CREEK, PHASE 6, SAN ILDEFON

Region III, Region III

2024₱133.0M
Ongoing (DPWH-reported)
No sat.

CONVERGENCE AND SPECIAL SUPPORT PROGRAM-SUSTAINABLE INFRA. PROJECTS ALLEVIATING GAPS(SIPAG)-FLOOD MITIGATION STRUCT. PROTECTING MAJOR/STRATEGIC PUBLIC BUILDINGS/FACILITIES-CONST. OF FLOOD CONTROL STRUCT. ALONG ANYATAM-MAPANIQUE CREEK, PHASE 7, SAN ILDEFON

Region III, Region III

2024₱128.3M
Ongoing (DPWH-reported)
View all 101 projects →

4. Implementation

Contract Amount

₱20,253,069.26

Progress

Reported complete (DPWH)

Start Date

May 2, 2023

Target End

September 25, 2023

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.