ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - TERTIARY ROADS, SIBONGA-DUMANJUG ROAD - K0075+065 - K0077+600
ORGANIZATIONAL OUTCOME 1: ENSURE SAFE AND RELIABLE NATIONAL ROAD SYSTEM, ASSET PRESERVATION PROGRAM, PREVENTIVE MAINTENANCE - TERTIARY ROADS, SIBONGA-DUMANJUG ROAD - K0075+065 - K0077+600 is a DPWH-tracked public work in Cebu 7th DEO, Region VII. Reported contract value: ₱120,193,875.88. Status: Past target date (DPWH On-Going). Contractor on record: NEWBIG FOUR J CONST INC FORMERLY: FOUR J CONST. Figures trace to dpwh.
Satellite images processing — before/after tiles will appear here after the next batch run.
Total Contract Cost