Flood Control and Drainage25HF0012

ORGANIZATIONAL OUTCOME 2: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, GUINABASAN RIVER, BARANGAY SANTA RITA, ASTURIAS, CEBU

ORGANIZATIONAL OUTCOME 2: CONSTRUCTION OF FLOOD MITIGATION STRUCTURE, GUINABASAN RIVER, BARANGAY SANTA RITA, ASTURIAS, CEBU is a DPWH-tracked public work in Cebu 3rd DEO, Region VII. Reported contract value: ₱96,375,597.42. Status: Past target date (DPWH On-Going). Contractor on record: VEN RAY CONST CORP. Figures trace to dpwh.

Cebu 3rd DEO, Region VII
Region: Region VII

Satellite images processing — before/after tiles will appear here after the next batch run.

Money Trail

1. Appropriation

Probable match · score 85%

UACS
18001
Amount
₱15,000,000.00 (GAA By-Object, amounts in ₱'000 × 1,000)
Program / description
Construction of Flood Control Structure, Tagamakan CIS, Asturias, Cebu
GAA fiscal year
FY2025
DBM GAA source document

2. Allotment

Agency-level releases for FY2025, not tied to this contract

Cebu 3rd DEO · SARO 1,540 (₱654,314,185,039.00) · NCA 1,270 (₱735,120,377,953.60)

3. Procurement & Award

No PhilGEPS award linked in the link table for this contract yet.

4. Implementation

Contract Amount

₱96,375,597.42

Progress

Past target date (DPWH On-Going)

Start Date

February 20, 2025

Target End

December 23, 2025

5. Audit

No COA audit observations linked to this project yet. See COA AAR sources.